This report explores the learning across the end-to-end energy system as part of the Trial Period 1 for Project LEO and TRANSITION.
This first set of Trials ran for 17 weeks, with 69 events, 18 assets, over 3 Bulk Supply Points (BSPs). The trials have predominately tested the ability of an asset to deliver a set amount of flexibility at a set time. There are 3 trial periods that last until January 2023 and this report of the findings of the first trial period from November 2021 to February 2022.
It gives a flavour of the challenges overcome in setting up a local market for flexibility and produces key learning and recommendations for each area.
Publication date;
12th October 2022
Authors;
Multiple Authors from Project LEO Partners and TRANSITION Team